Coastal Regulation Zone (CRZ) Norms

Context:

The Brihanmumbai Municipal Corporation (BMC) inspected a bungalow owned by a Union Minister for alleged violation of Coastal Regulation Zone (CRZ) norms.

Relevance:

GS III- Environment and Ecology

Dimensions of the Article
  1. What are CRZ norms?
  2. Salient Features of CRZ Rules:

What are CRZ norms?

  • In India, the Coastal Regulation Zone (CRZ) Rules govern human and industrial activity close to the coastline, in order to protect the fragile ecosystems near the sea.
  • They restrict certain kinds of activities — like large constructions, setting up of new industries, storage or disposal of hazardous material, mining, reclamation and bunding — within a certain distance from the coastline.
  • After the passing of the Environment Protection Act in 1986, CRZ Rules were first framed in 1991.
  • After these were found to be restrictive, the Centre notified new Rules in 2011, which also included exemptions for the construction of the Navi Mumbai airport and for projects of the Department of Atomic Energy.
  • In 2018, fresh Rules were issued, which aimed to remove certain restrictions on building, streamlined the clearance process, and aimed to encourage tourism in coastal areas.
  • In all Rules, the regulation zone has been defined as the area up to 500 m from the high-tide line.
  • While the CRZ Rules are made by the Union environment ministry, implementation is to be ensured by state governments through their Coastal Zone Management Authorities.

Salient Features of CRZ Rules 2018:

  • Allowing FSI as per current norms in CRZ areas: As per CRZ, 2011 Notification, for CRZ-II (Urban) areas, Floor Space Index (FSI) or the Floor Area Ratio (FAR) had been frozen as per 1991 Development Control Regulation (DCR) levels. In the CRZ, 2018 Notification, it has been decided to de-freeze the same and permit FSI for construction projects, as prevailing on the date of the new Notification. This will enable redevelopment of these areas to meet the emerging needs.
  • Densely populated rural areas to be afforded greater opportunity for development: For CRZ-III (Rural) areas, two separate categories have now been stipulated as below:
    • CRZ-III A – These are densely populated rural areas with a population density of 2161 per square kilometer as per 2011 Census. Such areas shall have a No Development Zone (NDZ) of 50 meters from the High-tide level (HTL) as against 200 meters from the High Tide Line stipulated in the CRZ Notification, 2011 since such areas have similar characteristics as urban areas.
    • CRZ-III B – Rural areas with population density of below 2161 per square kilometer as per 2011 Census. Such areas shall continue to have an NDZ of 200 meters from the High-tide level (HTL).
  •  Tourism infrastructure for basic amenities to be promoted: Temporary tourism facilities such as shacks, toilet blocks, change rooms, drinking water facilities etc. have now been permitted in Beaches. Such temporary tourism facilities are also now permissible in the “No Development Zone” (NDZ) of the CRZ-III areas as per the Notification. However, a minimum distance of 10 m from HTL should be maintained for setting up of such facilities.
  • CRZ Clearances streamlined: The procedure for CRZ clearances has been streamlined. Only such projects/activities, which are located in the CRZ-I (Ecologically Sensitive Areas) and CRZ IV (area covered between Low Tide Line and 12 Nautical Miles seaward) shall be dealt with for CRZ clearance by the Ministry of Environment, Forest and Climate Change. The powers for clearances with respect to CRZ-II and III have been delegated at the State level with necessary guidance.
  •  A No Development Zone (NDZ) of 20 meters has been stipulated for all Islands: For islands close to the main land coast and for all Backwater Islands in the main land, in wake of space limitations and unique geography of such regions, bringing uniformity in treatment of such regions, NDZ of 20 m has been stipulated.
  •  All Ecologically Sensitive Areas have been accorded special importance: Specific guidelines related to their conservation and management plans have been drawn up as a part of the CRZ Notification.
  •  Pollution abatement has been accorded special focus: In order to address pollution in Coastal areas treatment facilities have been made permissible activities in CRZ-I B area subject to necessary safeguards.
  •  Defence and strategic projects have been accorded necessary dispensation.

-Source: Livemint